How much does a warehouse cost to build in 2026? Texas filings put new dry warehouses at a median $75 per sq ft ($55 to $107); a 50,000 sq ft building runs $3.6 million to $6.1 million before land.
Those figures come from 609 new warehouse projects registered with the Texas Department of Licensing and Regulation from January 2025 to November 2026, checked against Rider Levett Bucknall’s Q3 2026 cost report ($75 to $370 per sq ft across 18 U.S. cities) and Department of Defense unit prices for the site work around the building.
Key takeaways
- New dry warehouses registered in Texas from January 2025 to November 2026 had a median estimated cost of $75 per sq ft and $1,500,000 per project; the middle half ran $55 to $107 per sq ft (TDLR TABS, n=609).
- Buildings of 50,000 to 99,999 sq ft had a median of $77 per sq ft and $5.6 million per project, with a median schedule of 12 months from start to completion (TDLR TABS, n=53).
- Scale pays off above 100,000 sq ft: the median fell to $61 per sq ft for 100,000 to 249,999 sq ft and $52 for 250,000 sq ft and up (TDLR TABS, n=114).
- RLB’s Q3 2026 hard-cost range for a warehouse is $75 to $155 per sq ft in Austin and Dallas, $150 to $230 in Los Angeles and $290 to $370 in Portland (RLB, Q3 2026).
- Site work outside the building can add about $608,705 to a 50,000 sq ft project: an 8 inch reinforced concrete truck apron at $180.15 per square yard, an asphalt truck court and a quarter-acre detention pond at $147,100.52 (DoD UFS 3-701-01, October 2025 prices).
- The BLS producer price index for new warehouse construction rose 5.5% from October 2025 to October 2026, to 250.628 (preliminary) (BLS PCU236221236221).
How much does a warehouse cost per square foot in 2026?
A new dry warehouse costs about $55 to $107 per sq ft to build, with a median of $75, in 609 Texas project registrations filed from January 2025 to November 2026. That is the registrant’s estimated construction cost divided by the registered floor area. It excludes land, and some records include site work while others do not.
| Project group (Texas registrations) | Projects | 25th percentile $/sq ft | Median $/sq ft | 75th percentile $/sq ft | Median project cost | Source |
|---|---|---|---|---|---|---|
| All new dry warehouses | 609 | $55 | $75 | $107 | $1,500,000 | TDLR TABS |
| Scope says pre-engineered metal or steel building | 114 | $56 | $75 | $103 | $862,500 | TDLR TABS |
| Scope says tilt-wall or tilt-up concrete | 90 | $45 | $69 | $88 | $5,480,734 | TDLR TABS |
| 100,000 sq ft and larger | 114 | $46 | $60 | $78 | $12,078,234 | TDLR TABS |
Texas has these numbers because Texas Government Code Section 469.101 requires accessibility plan review for a covered building when the estimated construction cost is at least $50,000, and the registration is public. Metal buildings had a median of $75 and tilt-up buildings $69, but the metal group’s median size was 9,946 sq ft against 91,751 sq ft for tilt-up, so the system mostly follows building size.

Online guides on page one of Google quote anything from $20 to $285 per sq ft without naming a source. The Texas median of $75 sits at the low end of RLB’s 2026 city ranges, which fits: RLB rates Austin and Dallas as its two lowest-cost U.S. warehouse markets, and 201 of the 609 Texas records are shells. For the broader cost-per-square-foot picture across building types, see our commercial construction cost per square foot guide.
How much does a warehouse cost by size?
Cost per sq ft holds near $77 to $79 up to 100,000 sq ft in Texas filings, then drops: the median was $61 for 100,000 to 249,999 sq ft and $52 for 250,000 sq ft and up. Big distribution buildings spread walls, docks and offices over more floor, and most of them are registered as shells. Median project cost climbs from $447,581 under 10,000 sq ft to $25.0 million at 250,000 sq ft and up.
| Building size (sq ft) | Projects | Middle half $/sq ft | Median $/sq ft | Median project cost | Median size (sq ft) | Median months, start to completion |
|---|---|---|---|---|---|---|
| Under 10,000 | 233 | $55 to $130 | $79 | $447,581 | 5,279 | 7 |
| 10,000 to 24,999 | 122 | $61 to $118 | $77 | $1,200,000 | 14,392 | 9 |
| 25,000 to 49,999 | 87 | $68 to $97 | $78 | $2,770,000 | 32,250 | 10 |
| 50,000 to 99,999 | 53 | $50 to $93 | $77 | $5,607,680 | 70,730 | 12 |
| 100,000 to 249,999 | 71 | $47 to $79 | $61 | $9,527,707 | 150,695 | 12 |
| 250,000 and up | 43 | $44 to $75 | $52 | $25,000,000 | 407,110 | 12 |
Source: TDLR TABS new-construction registrations, January 2025 to November 2026, pulled November 21, 2026; dry warehouses only, cold storage excluded. Dates are the planned start and completion entered at registration.
For a quick total, multiply your floor area by the band median and use the middle-half range as the low and high case. A 10,000 sq ft building at $77 is $770,000; a 100,000 sq ft building at $61 is $6.1 million. Both exclude land, racking and lift trucks.
What does a warehouse shell cost compared with a finished building?
A warehouse shell (slab, structure, walls, roof and a fire riser, with offices and tenant finishes left for later) ran a median $75 per sq ft in 201 Texas registrations that call the project a shell or speculative building. Records that do not say shell ran $81, and their middle half reached $118 against $80 for shells, because finished buildings carry offices, restrooms, lighting and HVAC.
| Scope | $/sq ft (middle half; median) | Records or basis | Source |
|---|---|---|---|
| Shell or speculative warehouse | $58 to $80; $75 | 201 Texas registrations | TDLR TABS |
| New warehouse, not described as a shell | $50 to $118; $81 | 408 Texas registrations | TDLR TABS |
| Warehouse with offices named in the scope | $66 to $126; $77 | 308 Texas registrations | TDLR TABS |
| Addition to an existing warehouse | $60 to $148; $97 | 38 Texas registrations | TDLR TABS |
| Cold storage warehouse (contrast) | $124 to $209; $179 | 8 Texas registrations | TDLR TABS |
| Military high-bay storage building over 15,000 sq ft (federal contrast) | $386.31 | 3 DoD projects, October 2025 prices, 65,879 sq ft reference size | DoD UFS 3-701-01 Table 2 |
The cold storage line rests on only 8 records, so treat it as a direction, not a budget. The federal figure is for military buildings with antiterrorism and other federal requirements, which is why it runs several times the Texas private median.
City permit valuations show the same pattern. The City of Austin publishes the job valuation and new floor area for every issued permit; six warehouse permits issued from 2024 to 2026 read like this:
| Austin permit (issued) | Scope as written in the permit | Sq ft | Valuation | $/sq ft |
|---|---|---|---|---|
| 2024-005712 BP (Jan 2024) | New shell warehouse, Building A | 87,467 | $8,500,000 | $97.18 |
| 2024-005713 BP (Jan 2024) | New shell warehouse, Building B | 83,492 | $8,500,000 | $101.81 |
| 2024-148676 BP (Nov 2024) | Concrete tilt-wall building with second-story office | 42,100 | $4,200,000 | $99.76 |
| 2024-130841 BP (Oct 2024) | Tilt-wall warehouse with office and associated site work | 72,260 | $10,000,000 | $138.39 |
| 2024-128817 BP (Nov 2024) | Office warehouse shell, not for occupancy | 17,919 | $895,950 | $50.00 |
| 2026-058058 BP (May 2026) | Pre-fabricated engineered building for office/warehouse | 78,000 | $2,500,000 | $32.05 |
Source: City of Austin Issued Construction Permits open data, queried November 21, 2026. Permits that repeat one campus valuation on several buildings, or show a $1 placeholder, were left out.
A shell budget is not the move-in cost: offices, restrooms and dock equipment follow, often funded partly by a tenant improvement allowance.
What does it cost to build a 50,000 sq ft warehouse?
A 50,000 sq ft warehouse budgets about $3.6 million to $6.1 million in this worked example, with a middle case of $5.2 million, or $73 to $123 per sq ft all-in before land. The building uses the Texas 50,000 to 99,999 sq ft band; the site lines use Department of Defense unit prices at the national average, October 2025.
Assumptions: a 200 ft by 250 ft single-story dry warehouse, docks along one 250 ft long wall, a 60 ft deep concrete apron and 75 ft of asphalt maneuvering space in front of the docks (a 135 ft truck court), and a quarter-acre detention pond.
| Line | Arithmetic | Low | Middle | High | Source |
|---|---|---|---|---|---|
| Building (TABS band) | 50,000 sq ft x $50 / $77 / $93 | $2,500,000 | $3,850,000 | $4,650,000 | TDLR TABS |
| Concrete truck apron, 8 in reinforced | 60 ft x 250 ft = 1,666.7 SY x $180.15 | $300,250 | UFS 3-701-01 item 85110-4-2 | ||
| Asphalt truck court, 3 in over 8 in stone, fine graded | 75 ft x 250 ft = 2,083.3 SY x ($41.15 + $31.63 + $4.67) | $161,354 | UFS items 85110-1-3, 85110-6-3, 93210-2-2 | ||
| Detention pond, 1/4 acre, 5 ft deep | 1 x $147,100.52 | $147,101 | UFS item 83210-4-2 | ||
| Construction subtotal | Building + site lines | $3,108,705 | $4,458,705 | $5,258,705 | Sum |
| Design and engineering | Subtotal x 9% (DoD P&D factor 1.09) | $279,783 | $401,283 | $473,283 | UFS 3-701-01 |
| Contingency | (Subtotal + design) x 7% | $237,194 | $340,199 | $401,239 | GSA, January 2024 |
| Total before land | $3,625,682 | $5,200,187 | $6,133,227 | ||
| All-in $/sq ft | Total / 50,000 | $72.51 | $104.00 | $122.66 | Arithmetic |
Check the building line against your own registration or bid: some Texas records include site work (TABS2026024257, a 49,156 sq ft Grayson County warehouse at $4,000,000, says “associated site work”), so if your contractor’s number already carries paving and detention, drop those lines rather than counting them twice. GSA uses 7% contingency for new capital construction and 10% for repair and alteration; our construction contingency guide covers how the reserve shrinks as design advances.
Not in the total: land, utility tap and impact fees, racking, lift trucks and financing. Add a fire pump or extra docks from the next table.
How much does location change warehouse cost?
Location moves warehouse hard cost more than any design choice: from $75 per sq ft at the low end in Austin and Dallas to $370 at the high end in Portland, almost 5 times. Rider Levett Bucknall’s Q3 2026 report also puts warehouses at $140 to $225 per sq ft of gross floor area in Washington, D.C. and $195 to $265 in Seattle. RLB’s figures are hard construction cost only, before soft costs and land.
| City | Low $/sq ft | High $/sq ft | 50,000 sq ft hard cost at that range |
|---|---|---|---|
| Austin | $75 | $155 | $3.8 million to $7.8 million |
| Dallas | $75 | $155 | $3.8 million to $7.8 million |
| Las Vegas | $80 | $180 | $4.0 million to $9.0 million |
| Miami | $80 | $160 | $4.0 million to $8.0 million |
| Phoenix | $85 | $170 | $4.2 million to $8.5 million |
| Charlotte | $135 | $215 | $6.8 million to $10.8 million |
| Boston | $140 | $230 | $7.0 million to $11.5 million |
| Denver | $140 | $225 | $7.0 million to $11.2 million |
| Nashville | $140 | $215 | $7.0 million to $10.8 million |
| Washington, D.C. | $140 | $225 | $7.0 million to $11.2 million |
| Los Angeles | $150 | $230 | $7.5 million to $11.5 million |
| Chicago | $155 | $245 | $7.8 million to $12.2 million |
| New York | $155 | $250 | $7.8 million to $12.5 million |
| Honolulu | $160 | $305 | $8.0 million to $15.2 million |
| Minneapolis | $160 | $245 | $8.0 million to $12.2 million |
| San Francisco | $160 | $255 | $8.0 million to $12.8 million |
| Seattle | $195 | $265 | $9.8 million to $13.2 million |
| Portland | $290 | $370 | $14.5 million to $18.5 million |
Source: Rider Levett Bucknall, North America Quarterly Cost Report Q3 2026, Indicative Construction Costs, Industrial: Warehouse (hard cost, U.S. dollars per sq ft of gross floor area). Multiplication by CB&C.
The Texas registration median of $75 sits at the low end of RLB’s $75 to $155 range for Austin and Dallas, a useful cross-check from two independent sources. If your site is in a city RLB does not list, start from the nearest listed city and ask two local builders to confirm the range before you commit to a land price.
What drives warehouse cost up or down?
Six items move a warehouse budget most: floor area and shape, clear height, slab thickness, dock count, fire protection and site work. The table prices each one from a public record or agency unit price, so you can see what a change does to a 50,000 sq ft project.
| Driver | Priced item | Unit cost | Effect on a 50,000 sq ft project | Source |
|---|---|---|---|---|
| Slab thickness | 6 in vs 8 in concrete, state DOT average low bids, 2024 | $9.07 vs $9.80 per sq ft | About +$36,500 to go from 6 to 8 in | South Dakota DOT 2024 Bid Item Price Report |
| Dock positions | Dock leveler, furnished and installed (federal 2025 orders) | $15,508 (6 levelers) and $17,268 (2 hydraulic levelers) each | About $155,000 to $173,000 for 10 docks, levelers only | USAspending N4008525F0815; 36C26126P0173 |
| Sprinklers | Sprinkler installs in two existing Texas warehouses, registered June 2021 | $5.66 and $8.12 per sq ft | About $283,000 to $406,000 if not in the base bid | TDLR TABS (TABS2021017204, TABS2021017178) |
| Fire pump | Electric 1,000 GPM; diesel 2,000 GPM, installed | $97,687.93; $220,513.50 | Only when the water main cannot meet the sprinkler demand | UFS items 84472-2-1, 84472-1-3 |
| Truck court | 8 in reinforced concrete pavement | $180.15 per SY ($20.02 per sq ft) | $300,250 for a 60 ft by 250 ft apron | UFS item 85110-4-2 |
| Stormwater | Detention pond, 5 ft deep, fenced and seeded | $147,100.52 (1/4 acre); $295,269.51 (1/2 acre) | Doubles if the city requires a half-acre pond | UFS items 83210-4-2, 83210-4-4 |
| Metro | Warehouse hard cost range | $75 to $155 (Austin) vs $290 to $370 (Portland) | $3.8 million to $18.5 million for the building alone | RLB Q3 2026 |
Three rows need context. The dock leveler and sprinkler prices come from work in existing buildings, which can price differently from the same item in a new building’s base bid. The fire pump and pond prices are DoD national averages as of October 1, 2025, and DoD says its unit costs are for planning, not for an individual project estimate.
How much does clear height add?
Every extra foot of clear height adds wall area equal to the building perimeter: 900 sq ft of wall per foot on a 200 ft by 250 ft footprint. Going from 28 ft to 36 ft adds at least 7,200 sq ft of wall, plus longer columns and a sprinkler design for taller storage. The payoff is storage volume, so compare taller buildings on cost per cubic foot, not per square foot.
| Clear height | Minimum exterior wall area (sq ft) | Storage volume (cu ft) | Cost per cu ft at a flat $77 per sq ft |
|---|---|---|---|
| 24 ft | 21,600 | 1.2 million | $3.21 |
| 28 ft | 25,200 | 1.4 million | $2.75 |
| 32 ft | 28,800 | 1.6 million | $2.41 |
| 36 ft | 32,400 | 1.8 million | $2.14 |
| 40 ft | 36,000 | 2.0 million | $1.93 |
Arithmetic by CB&C for a 200 ft by 250 ft (50,000 sq ft) footprint; wall area excludes parapets and the depth of the roof structure. The last column holds cost per sq ft flat to show the volume effect only; in practice a taller building costs somewhat more per sq ft.
Sprinklers are the other height-driven cost. Under IBC 2024 Section 903.2.9, a Group S-1 storage building needs automatic sprinklers once one fire area exceeds 12,000 sq ft, and rack storage above the heights in the fire code moves the design to a storage-specific approach such as ESFR (early suppression, fast response) under NFPA 13. Our fire sprinkler system cost guide has the per-square-foot records, and our concrete slab cost guide prices the floor.
How long does it take to build a warehouse?
A new warehouse takes a median 10 months from construction start to completion in Texas registrations, with the middle half between 7 and 12 months. Buildings under 10,000 sq ft median 7 months; 50,000 to 99,999 sq ft median 12 months; 250,000 sq ft and up median 12 months.
Those are planned dates entered at registration, so add design and permitting time ahead of them. Schedule matters to cost because the warehouse price index keeps moving: the BLS producer price index for new warehouse building construction rose from 237.470 in October 2025 to 250.628 in October 2026 (preliminary), a 5.5% increase (BLS PCU236221236221). Our construction price index tracker updates that series monthly.
Prices rose while volume fell: private warehouse construction ran at $53.1 billion (seasonally adjusted annual rate, preliminary) in August 2026, down 8.1% from $57.8 billion a year earlier, according to the Census Bureau’s value put in place series. Less building has not yet meant cheaper building.
Which budget number should you use?
Use the source that matches what you know about the project today. Before you have a site, a size-band median from 609 Texas records is enough to test feasibility; once you have a city and a site plan, move to RLB’s range for one of its 18 cities and price the site lines; once you have drawings, only contractor bids count.
| If this is true | Use this number | Why |
|---|---|---|
| You only know the size | Texas size-band median, low and high at the 25th and 75th percentiles | Real filed projects, 609 records |
| You know the metro and it is one of RLB’s 18 U.S. cities | RLB Q3 2026 low and high for that city | City-specific hard cost, dated Q3 2026 |
| The building is a spec shell with no tenant | The shell row, then a separate tenant improvement budget | Shell excludes offices and finishes |
| The site is raw land | Add truck court, detention and utilities (about $609,000 in the worked example) | Many building figures exclude site work |
| One S-1 fire area will exceed 12,000 sq ft | Confirm sprinklers and water supply are in the bid; add a fire pump if flow is short | IBC 2024 Section 903.2.9 |
| It is cold storage | Do not use dry warehouse rows; price insulated panels, refrigeration and slab heating separately | Texas cold records ran about twice the dry median |
| You have two or more bids | The bids, compared line by line | Bids reflect your drawings, site and market |
When bids arrive, check that each one carries the same clear height, slab thickness, dock count and sprinkler design before you compare totals; our guide on how to compare construction bids has a checklist. For the shell choices behind these numbers (tilt-up vs precast vs metal, FF/FL floor flatness measured under ASTM E1155, dock layout), see our warehouse construction guide, and for a metal shell the steel building prices page breaks out the kit and erection costs.
Refrigerated space costs far more, as our cold storage warehouse construction guide shows, and dock layout follows loading dock dimensions.
How we compiled this
We pulled 844 Texas Architectural Barriers project registrations whose name matched warehouse, distribution, logistics or industrial on November 21, 2026, read each project page, and kept 655 new or addition projects after removing fit-outs, self-storage, manufacturing plants, other building types and records outside $20 to $600 per sq ft. We added RLB’s Q3 2026 city ranges, 6 City of Austin permit records, DoD unit prices dated October 1, 2025, two 2025 federal dock leveler orders and the BLS warehouse price index. Estimated costs are registrants’ estimates, not final costs, and are not escalated; nothing here comes from testing, surveys or our own projects.
Frequently asked questions
How much does it cost to build a 10,000 sq ft warehouse?
About $610,000 to $1,180,000 for the building, with a median of $770,000, based on 122 Texas registrations of 10,000 to 24,999 sq ft filed January 2025 to November 2026 at $61 to $118 per sq ft. Add land, any site work the estimate leaves out, design fees and a contingency of about 7%.
How much does it cost to build a 100,000 sq ft warehouse?
About $4.7 million to $7.9 million for the building in Texas, using the 100,000 to 249,999 sq ft band of 71 registrations at $47 to $79 per sq ft. In higher-cost metros, RLB’s Q3 2026 range of $195 to $265 per sq ft for Seattle puts the same building at $19.5 to $26.5 million.
Is a metal building warehouse cheaper than tilt-up?
No, not per square foot in Texas filings. Registrations describing a pre-engineered metal or steel building had a median of $75 per sq ft, and tilt-wall records had $69. The groups differ in size, a median 9,946 sq ft for metal against 91,751 sq ft for tilt-up, so the filings show metal on small buildings and tilt-up on large ones.
Does warehouse construction cost include land?
No. Texas registrations, Austin permit valuations and RLB’s Q3 2026 ranges all measure construction only. Land, utility tap and impact fees, racking, lift trucks and financing are separate. Site work is mixed: some Texas records include paving and detention, so ask whether your estimate does before adding the roughly $609,000 of site lines from the 50,000 sq ft example.
How long does it take to build a warehouse?
A median 10 months from start to completion in 609 Texas registrations, with the middle half between 7 and 12 months. Buildings of 50,000 to 99,999 sq ft planned a median 12 months. Those are construction dates only; design, permitting and utility work come before the start date.
Why do online warehouse cost estimates differ so much?
They measure different things and rarely say which. A $20 per sq ft figure is close to a steel kit price, while $285 per sq ft is close to RLB’s Q3 2026 high of $305 for a warehouse in Honolulu. Always ask whether a figure is shell or finished, includes site work and soft costs, and which city and year it describes.
Sources
- Texas Department of Licensing and Regulation, TABS project search and project pages, registrations January 2025 to November 2026, accessed November 21, 2026.
- Texas Legislature, Government Code Section 469.101, accessed November 21, 2026.
- Rider Levett Bucknall, North America Quarterly Cost Report, Q3 2026, accessed November 21, 2026.
- U.S. Department of Defense, UFS 3-701-01 DoD Facilities Pricing Guide (June 6, 2026) and data tables (prices as of October 1, 2025), accessed November 21, 2026.
- City of Austin, Issued Construction Permits open data, accessed November 21, 2026.
- U.S. Bureau of Labor Statistics, PPI for new warehouse building construction (PCU236221236221), October 2026 preliminary, accessed November 21, 2026.
- USAspending.gov, award N4008525F0815 and award 36C26126P0173, accessed November 21, 2026.
- South Dakota Department of Transportation, 2024 Bid Item Price Report (issued March 31, 2025), accessed November 1, 2026.
- U.S. General Services Administration, Q&A: Cost Estimating and Cost Management Principles (January 18, 2024), accessed November 21, 2026.
- International Code Council, 2024 International Building Code, Chapter 9, accessed November 21, 2026.
- U.S. Census Bureau, Value of Construction Put in Place, private warehouse series, accessed November 21, 2026.