A payment bond is a surety’s guarantee that the contractor will pay its subcontractors, laborers and suppliers; if it does not, an unpaid claimant collects from the surety, up to the bond amount, usually 100% of the contract price.
Key takeaways
- Federal construction contracts over $150,000 need a payment bond equal to 100% of the original contract price under FAR 28.102-2; the Miller Act text, 40 U.S.C. 3131, still reads more than $100,000.
- From $35,000 to $150,000, a federal contracting officer picks two or more payment protections, such as a payment bond or an irrevocable letter of credit, under FAR 28.102-1(b).
- A sub-subcontractor or a supplier to a subcontractor on a federal job must give the prime written notice within 90 days of its last work and sue within 1 year, under 40 U.S.C. 3133(b).
- State Little Miller Act notice windows in our sample run from 90 days (Virginia, Florida, Arizona) to 120 days (New York State Finance Law 137) and 180 days (ORS 279C.605, Oregon); Texas counts in months.
- Public bid records from 2014 to 2018 priced the combined payment and performance bond at 0.10% to 1.77% of the bid (Transbay Joint Powers Authority, City of Longview, Texas).
What does a payment bond guarantee, and who are the parties?
A payment bond guarantees that people who supply labor, materials and equipment to the job get paid. The contractor (principal) and the surety bind themselves to the owner (obligee), and the claimants are the subcontractors and suppliers. On federal work the bond is Standard Form 25A (Rev. 10/2023); on private and many public jobs it is the AIA A312-2010 Payment Bond.
| Role | Who it is | What the bond does for it | Source |
|---|---|---|---|
| Principal | The prime contractor | Buys the bond and is bound jointly and severally with the surety to pay for labor, materials and equipment | A312-2010 Section 1; 40 U.S.C. 3131(b) |
| Surety | An insurance company; federal bonds need one of the 249 companies on Treasury Circular 570 (effective Aug. 1, 2026) | Pays valid claims up to the penal sum | FAR 52.228-15(d) |
| Obligee | The project owner | Keeps unpaid trades off its property and out of its budget; under A312-2010 the surety must defend and indemnify the owner against those claims (Sections 3 and 4) | AIA A312-2010 |
| Claimant | Subcontractors, sub-subcontractors, suppliers, laborers; under A312-2010 also equipment rental, utilities and design services | Gets a right to sue the surety instead of liening public property | A312-2010 Section 16.2; 40 U.S.C. 3133(b) |
The bond amount is usually the full contract price. Federal law sets the payment bond at the total amount payable under the contract unless the contracting officer finds in writing that this is impractical, and never less than the performance bond (40 U.S.C. 3131(b)(2)). California sets it at not less than 100% of the total payable (Cal. Civ. Code 9550 to 9554), and Texas at the contract amount (Gov’t Code 2253.021(c)).
The bond does not protect the owner against a contractor that stops work; that is the job of the performance bond, compared side by side in our performance bond guide. This page summarizes statutes, regulations, bond forms and bid records checked in November 2026. It is not legal advice: the bond attached to your contract and the statute in your state control, and a construction attorney can apply them to your claim.
Who can claim on a payment bond?
On a federal job, anyone with a direct contract with the prime contractor or with one of its subcontractors can claim. That covers first-tier subcontractors and suppliers, plus sub-subcontractors and suppliers to subcontractors, who must also give the 90-day notice. Someone further down, such as a supplier to a supplier, has no direct contract with either and falls outside the text of 40 U.S.C. 3133(b).
| Claimant | Federal (Miller Act) | AIA A312-2010 (private) | Texas public work |
|---|---|---|---|
| Subcontractor or supplier with a contract with the prime | Covered; sue once unpaid 90 days after last work | Covered; send a Claim to the surety (Section 5.2) | Covered; claim notice to prime and surety by the 15th day of the third month (2253.041) |
| Sub-subcontractor or supplier to a subcontractor | Covered; written notice to prime within 90 days | Covered; notice of non-payment to the contractor within 90 days, then a Claim (Section 5.1) | Covered; adds a second-month notice to the prime (2253.047) |
| Supplier to a supplier, or a sub of a sub-subcontractor | Outside the statute text (no direct contract with the prime or a subcontractor) | Covered only if it rightfully asserted a mechanic’s lien claim (Section 16.2) | Outside the statute text: beneficiaries need a direct contract with the prime or a subcontractor (2253.021(c)) |
| Laborer employed by the prime or a sub | Covered | Covered (Section 5.2 for the contractor’s employees) | Covered; the 2253.047 notice does not apply to an individual claiming wages |
Whether a given company counts as a “subcontractor” or only a “supplier” is decided by courts on the facts of each job, so the tier test can be closer than the table suggests. The federal statute and the Virginia statute (Va. Code 2.2-4341(B)) use the same direct-contract wording, which is why the 90-day notice applies only to the second tier.
What does the Miller Act require?
The Miller Act, now 40 U.S.C. 3131 to 3134, requires a performance bond and a payment bond before award of a federal construction contract. The statute says more than $100,000; the Federal Acquisition Regulation applies $150,000 as amended through FAC 2026-01, and from $35,000 to $150,000 it requires alternative payment protection. The bonds are delivered before work starts (FAR 52.228-15(c)).
| Contract value (federal construction) | Payment protection required | Amount | Source |
|---|---|---|---|
| $35,000 or less | None required by FAR 28.102 | Not applicable | FAR 28.102-1 |
| Over $35,000 to $150,000 | Contracting officer selects two or more of: payment bond, irrevocable letter of credit, tripartite escrow, certificates of deposit, 28.204 securities; contractor furnishes one | 100% of the original contract price plus 100% of increases | FAR 28.102-1(b); 28.102-2(c) |
| Over $150,000 | Payment bond (SF 25A) and performance bond (SF 25) | 100% of the original contract price plus 100% of increases; payment bond never below the performance bond | FAR 28.102-2(b) |
| Statute text | Bonds on contracts over $100,000; alternatives over $25,000 up to $100,000 | Total amount payable by the contract | 40 U.S.C. 3131; 3132 |
| Waivers | Work in a foreign country; certain cost-type and vessel contracts of the military departments, Transportation and Commerce | Not applicable | 3131(d); 40 U.S.C. 3134 |
What must a Miller Act notice say, and how is it served?
A second-tier claimant’s notice must reach the prime within 90 days of its last labor or material, state the amount claimed “with substantial accuracy” and name the party it supplied or worked for (40 U.S.C. 3133(b)(2)). It must be served by any means that gives written third-party verification of delivery, such as certified mail or a courier signature, or the way a U.S. marshal serves a summons.
- Name of the claimant and of the party it furnished labor or material to.
- Amount claimed, stated with substantial accuracy.
- Delivery to the prime at any office or place of business, or its residence, with third-party proof of delivery.
- Timing: counted from the last day of labor or material for which the claim is made, not from invoice or due dates.
Where and when must a Miller Act suit be filed?
A Miller Act suit must be filed within 1 year after the claimant’s last labor or material, in the U.S. District Court for the district where the contract was performed, regardless of the amount (40 U.S.C. 3133(b)(3), (4)). It is filed in the name of the United States for the use of the claimant, and the Government pays none of its costs (3133(b)(5)).
A waiver of the right to sue is void unless it is in writing, signed by the claimant and executed after the claimant furnished the work (3133(c)), so a waiver clause signed in a subcontract before work starts does not bar a Miller Act claim. How waivers travel with progress payments is explained in our lien waiver guide. Federal agencies also may not withhold progress payments because subs are unpaid; after completion, on the surety’s written notice, the contracting officer withholds final payment (FAR 28.106-7).
What are the Little Miller Act payment bond rules by state?
States set their own payment bond statutes for public work, called Little Miller Acts, because mechanics liens generally cannot attach to public property. Thresholds in the eight jurisdictions we read run from $25,000 (California, Texas) to $500,000 (Virginia), and lower-tier notice windows from 90 to 180 days. The table links each statute; local rules and agency specs can add bonds below these floors.
| Jurisdiction | Payment bond required on contracts | Notice from a claimant without a contract with the prime | Deadline to sue | Statute (read Nov. 2026) |
|---|---|---|---|---|
| Federal | Over $150,000 (FAR); over $100,000 (statute text) | Written notice to the prime within 90 days of last work | 1 year after last work, U.S. District Court | 40 U.S.C. 3133 |
| Arizona | Covered public contracts under 34-222(A), at the full contract amount; NASBP lists $100,000 (non-highway) | Preliminary 20-day notice plus a 90-day notice with third-party verified delivery | 1 year after last work | A.R.S. 34-222; 34-223 |
| California | Over $25,000 (not state entities) | Preliminary notice to the public entity and direct contractor (9300); if missed, notice to surety and principal within 15 days after a recorded notice of completion, or 75 days after completion | No later than 6 months after the stop payment notice period ends | Civ. Code 9550; 9300; 9560; 9558 |
| Florida | Over $100,000 on state contracts; local owners may exempt $200,000 or less | Notice to the contractor within 45 days of starting; sworn notice of nonpayment from day 45 after first furnishing to 90 days after final furnishing | 1 year after last labor or delivery | Fla. Stat. 255.05 |
| New York (state) | Required; may be dispensed with under $100,000 | Written notice within 120 days of last work, personally or by registered mail | 1 year after the public owner completes and accepts the work | State Finance Law 137 |
| Oregon | Over $100,000 ($50,000 transportation) | Every claimant: notice of claim within 180 days, registered or certified mail or hand delivery | 2 years after last work | ORS 279C.380, 279C.600 to 279C.610 |
| Texas | Over $25,000; over $50,000 for a city | Every claimant: notice of claim to prime and surety by the 15th day of the third month after each month of work; lower tiers also a second-month notice to the prime | From the 61st day after the notice to 1 year after it was mailed | Gov’t Code 2253.021, .041, .047, .073, .078 |
| Virginia | Over $500,000 ($350,000 state-funded transportation) | Written notice within 90 days by registered or certified mail; retainage claims exempt from that limit | 1 year after last work | Va. Code 2.2-4337; 2.2-4341 |
The National Association of Surety Bond Producers’ survey of state bond thresholds (January 1, 2024) lists the other states, from $1,000 on some highway work to $500,000; it names Ohio and West Virginia as having no threshold. Treat that list as a pointer to the statute, not a substitute. A threshold table for federal work and 10 states, with Circular 570 surety counts, is in our construction surety bond statistics.
How do payment bonds work on private jobs?
No statute read for this page makes a private owner require a payment bond; the owner’s contract, its lender or the GC’s subcontract does, usually naming the AIA A312-2010 form. On those jobs the bond’s own text sets the claim steps: a 90-day notice for lower tiers, a 60-day surety answer and a 1-year suit limit, with any conflicting statute reading in under Section 14.
- Get the bond: Section 15 makes the contractor and owner furnish a copy to any potential beneficiary who asks.
- Notice (no direct contract with the contractor): written notice of non-payment to the contractor within 90 days after last labor or materials, stating the amount and whom you supplied (Section 5.1.1). An owner’s notice also counts (Section 6).
- Claim to the surety at the address on its signature page (Sections 5.1.2, 5.2, 13), with the eight items in Section 16.1: your name, who you supplied, the contract or purchase order, a description, your last work date, total earned, payments received and amount unpaid.
- Surety answer: within 60 days after receiving the Claim, stating undisputed amounts and the basis for disputing the rest, and paying the undisputed amounts (Sections 7.1, 7.2). If it fails, it owes your reasonable attorney’s fees from then on (Section 7.3).
- Suit: in a court in the state where the project sits, within 1 year of the earlier of your Claim date or the last labor or materials furnished by anyone under the contract (Section 12).
The 1-year clock in Section 12 can start before your own Claim if the project finishes first, so a supplier who claims late in a job may have less than a year. Section 10 adds that the owner has no obligation to claimants under the bond. Where A312 sits among the other AIA forms is covered in our AIA contract documents guide.
Florida gives private owners a statutory reason to bond: a payment bond of at least the original contract price, attached to the recorded notice of commencement, exempts the owner from liens under Fla. Stat. 713.23, with the same 45-day and 90-day notices and a 1-year suit limit. The recording steps are in our Florida notice of commencement guide.
How does a payment bond claim work, step by step?
Every regime above follows the same order: get the bond, date your last work, serve the notice inside the window, send the claim to the surety, wait out the response period, then sue before the limit. The worked example uses one supplier whose last delivery was Wednesday, March 18, 2026, counted in calendar days with Python’s date library.
- Request the bond and the surety’s name and address. Federal: the contracting officer furnishes the surety name, penal amount and a copy on request (FAR 28.106-6), and a certified copy on an affidavit of nonpayment (40 U.S.C. 3133(a)). Texas bonds must print the surety’s notice address (2253.021(f)).
- Fix your last-work date from delivery tickets or daily logs; every federal, Arizona, Virginia and Oregon clock runs from it.
- Serve notice by a tracked method: third-party verified delivery (federal, Arizona), registered or certified mail (Virginia, Oregon), or mail to the prime and surety with a sworn statement of account (Texas 2253.041).
- Send the claim with the contract or purchase order, invoices, payments received and the unpaid balance.
- Track the response period: 60 days for an A312-2010 surety answer; in Texas, suit opens on the 61st day after the notice (2253.073).
- Sue before the limit, in the right court: U.S. District Court for federal jobs; state court where the project sits under A312-2010.
| Step | Federal (Miller Act) | Texas public work | Private, AIA A312-2010 |
|---|---|---|---|
| Last delivery | Mar 18, 2026 | March 2026 deliveries | Mar 18, 2026 |
| Early notice | Not required | Second-month notice to prime by May 15, 2026 (2253.047) | Not required |
| Notice deadline | Jun 16, 2026 (day 90) | Claim notice to prime and surety by Jun 15, 2026 (2253.041) | Notice of non-payment by Jun 16, 2026; claim sent Jun 10, 2026 in this example |
| Earliest suit | Jun 17, 2026 (unpaid after 90 days) | Aug 15, 2026 (61st day after Jun 15 notice) | After the surety’s answer, due Aug 9, 2026 (60 days) |
| Last day to sue | Mar 18, 2027 | Jun 15, 2027 | Jun 10, 2027, or earlier if the last work by anyone on the contract came before the claim |
| Rule | 40 U.S.C. 3133(b) | Gov’t Code 2253.041, .047, .073, .078 | A312-2010 Sections 5, 7, 12 |
The same delivery would give the supplier until July 16, 2026 to notify under New York’s 120-day rule and until September 14, 2026 under Oregon’s 180-day rule, with an Oregon suit due by March 18, 2028. If the supplier is also owed retainage, Virginia exempts retainage claims from its 90-day notice (2.2-4341(B)); how retainage is held and released is covered in our retainage guide.
How much does a payment bond cost?
Public bid records price the payment bond together with the performance bond as one line: 0.10% to 1.77% of the bid on 10 priced lines from 2014 to 2018, and 0.80% on a 2018 school GMP. The Congressional Research Service (R42037, July 2025) cites 1.5% to 3.0% of the contract amount. The contractor pays the premium and prices it into its bid.
| Public record | Date | Bid or GMP | Payment and performance bond line | Rate | Source |
|---|---|---|---|---|---|
| Transbay Joint Powers Authority (TJPA), structural concrete, two bidders | Feb 11, 2014 | $48,174,750; $78,741,515 | $289,049; $787,415 | 0.60%; 1.00% | TJPA TG07.2 tab |
| TJPA, fireproofing, three bidders | Sep 18, 2014 | $8,594,839; $8,908,096; $7,253,160 | $64,461; $8,908; $87,038 | 0.75%; 0.10%; 1.20% | TJPA TG16.8 tab |
| TJPA, miscellaneous metals | Jan 22, 2015 | $11,528,241 | $115,282 | 1.00% | TJPA TG07.3 tab |
| City of Longview, Texas, street striping, four bids | Jul 25, 2018 | $68,224.72 to $169,290.48 | $705 to $3,000 | 0.93% to 1.77% (our arithmetic) | Bid 1718-25 tab |
| Henderson County, North Carolina, Edneyville Elementary GMP | Apr 2018 | $21,852,605 | $174,821; subcontractor bonds a further $235,933 at 1.25% | 0.80% | Board packet |
The small Longview bids, all under $170,000, ran 0.93% to 1.77%, while the TJPA bids above $7 million mostly ran 0.60% to 1.20%, consistent with rates falling as contract size rises (our reading of a small sample). If the SBA Surety Bond Guarantee Program backs the bonds, on contracts up to $9 million or $14 million federal, the contractor also pays SBA 0.6% of the contract price.
| Line on a $2,000,000 public contract | Rate | Amount | Source |
|---|---|---|---|
| Bond premium at the TJPA low rate | 0.60% | $12,000 | TJPA TG07.2, 2014 |
| At the Henderson County GMP rate | 0.80% | $16,000 | Henderson County, 2018 |
| At 1.00% | 1.00% | $20,000 | TJPA TG07.3, 2015 |
| At the Longview high rate | 1.77% | $35,400 | Longview, 2018 |
| At the top of the CRS range | 3.0% | $60,000 | CRS R42037, 2025 |
| SBA contractor fee, if SBA guarantees the bonds | 0.6% of contract price | $12,000 | SBA |
| $200,000 change order: added bond amount, federal job | 100% of the increase | $200,000 | FAR 28.102-2(b)(2) |
| Added premium on that change at 1.00% | 1.00% | $2,000 | Rate from TJPA TG07.3 |
Seller pages that call the payment bond free when bundled describe the same thing the bid tabs show: one premium covers both bonds. Where only a payment bond is required, such as a Texas county job between $25,000 and $100,000 (2253.021), it is priced on its own. Bid security comes earlier and is covered in our bid bond guide.
Payment bond vs performance bond vs mechanics lien: what is the difference?
A payment bond protects the people who supply the job; a performance bond protects the owner if the work is not finished; a mechanics lien is the unpaid trade’s claim against private property itself. On public work the payment bond replaces the lien, and on a bonded Florida private job it can replace it too (Fla. Stat. 713.23).
| Item | Payment bond | Performance bond | Mechanics lien |
|---|---|---|---|
| Protects | Subs, suppliers, laborers | The owner | The unpaid claimant, secured by the property |
| Who claims | Claimants by tier (40 U.S.C. 3133(b); A312-2010 Section 16.2) | Only the owner (A312-2010 Performance Bond Section 9) | Claimants who meet the state lien statute |
| Public property | Yes, the usual remedy | Yes | Generally no |
| Federal amount | 100% of original price, never below the performance bond | 100% of original price | Not available |
| Typical suit limit | 1 year (federal, A312); 2 years (Oregon) | 2 years under A312-2010 Section 11 | Set by state; filing deadlines in our mechanics lien laws by state report |
Which payment bond rule applies to your project?
Start with who owns the project, then the contract value, then your tier. The table pairs common situations with the rule, its deadline and its source. Where no statute applies, the bond attached to the contract decides, so read its notice and suit clauses before relying on any row.
| If | Then | Rule |
|---|---|---|
| Federal construction contract over $150,000 | Miller Act bond (SF 25A) at 100%; tier 2 notice in 90 days, suit within 1 year | FAR 28.102-1; 40 U.S.C. 3133 |
| Federal contract over $35,000 up to $150,000 | Bond or alternative, such as a letter of credit; ask the contracting officer which one was furnished | FAR 28.102-1(b) |
| State or local public job | That state’s Little Miller Act; thresholds $25,000 to $500,000 and lower-tier notice 90 to 180 days in our sample | State table above |
| Texas public job | Monthly notices: 15th day of the second and third month after each month of work | Gov’t Code 2253.041, .047 |
| Private job with a bond in the contract | The bond form; under AIA A312-2010: notice 90 days, answer 60 days, suit within 1 year | A312-2010 Sections 5, 7, 12 |
| Private job with no bond | Mechanics lien on the property, by state statute | State lien deadlines |
| Asked to sign a bond-rights waiver before starting work on a federal job | Void unless written, signed and executed after you furnished the work | 40 U.S.C. 3133(c) |
| Owner of a private Florida job that wants lien protection | Require a bond of at least the contract price and attach it to the notice of commencement | Fla. Stat. 713.23 |
Most owners require it together with a performance bond, and subs on private jobs rely on lien waivers instead.
How we compiled this
We read 33 documents: four Miller Act sections, five FAR sections and the SF 25A form page, the AIA A312-2010 text, 14 statute sections from seven states, an industry threshold survey, five public bid records, a CRS report, the SBA program page and Treasury Circular 570, mostly on November 15, 2026 and the rest on November 2 and October 18. Seller-site premium figures and case law we did not read were left out. Bid-tab rates, the cost example and the dates are our arithmetic, under our editorial standards.
Frequently asked questions
Who pays for a payment bond?
The prime contractor buys the bond and pays the premium, then builds it into its price, so the owner pays through the contract sum. Public bid tabs show it as one line with the performance bond: 0.60% to 1.20% on Transbay Joint Powers Authority bids from 2014 to 2015 and 0.80% on Henderson County, North Carolina’s 2018 school GMP. If SBA guarantees the bond, the contractor also pays SBA 0.6% of the contract price.
How long do you have to file a Miller Act claim?
A supplier or sub-subcontractor without a contract with the prime must give the prime written notice within 90 days of its last labor or material. Any claimant must sue within 1 year after its last labor or material, in the U.S. District Court where the contract was performed, under 40 U.S.C. 3133(b). A first-tier claimant needs no notice but can sue only once 90 days pass unpaid.
Can a third-tier supplier claim on a payment bond?
On a federal job, 40 U.S.C. 3133(b) gives a right of action only to people with a direct contract with the prime or with a subcontractor, so a supplier to a supplier falls outside the text. Under the AIA A312-2010 private form, Section 16.2 adds anyone who rightfully asserted a mechanic’s lien claim, so a lower-tier claimant with lien rights may still qualify.
Is a payment bond required on private projects?
No statute read for this page makes a private owner require one; the contract, the lender or the GC’s subcontract does. Florida gives owners a reason: under Fla. Stat. 713.23, a payment bond of at least the original contract price, attached to the recorded notice of commencement, exempts the owner from liens, and claimants then follow 45-day and 90-day notices and a 1-year suit limit.
Can you sue the owner on a payment bond?
Generally no. The federal statute makes the Government liable for none of the costs of a Miller Act suit (40 U.S.C. 3133(b)(5)), Texas says the state is not liable for costs (Gov’t Code 2253.072), and AIA A312-2010 Section 10 says the owner has no obligations to claimants under the bond. The claim runs against the contractor and its surety, up to the bond amount.
How long does a surety have to answer a payment bond claim?
Under the AIA A312-2010 Payment Bond, the surety must answer within 60 days after receiving the Claim, stating undisputed amounts and the basis for disputing the rest, and pay the undisputed amounts (Sections 7.1 and 7.2). If it misses that duty, Section 7.3 makes it pay the claimant’s reasonable attorney’s fees incurred afterward. Texas lets the claimant sue if unpaid before the 61st day after notice.
Sources
- 40 U.S.C. 3131, Bonds of contractors of public buildings or works, Legal Information Institute, Cornell Law School. Accessed 2026-11-15.
- 40 U.S.C. 3132, Alternatives to payment bonds provided by Federal Acquisition Regulation, Legal Information Institute, Cornell Law School. Accessed 2026-11-15.
- 40 U.S.C. 3133, Rights of persons furnishing labor or material, Legal Information Institute, Cornell Law School. Accessed 2026-11-15.
- 40 U.S.C. 3134, Waiver of bonds for certain contracts, Legal Information Institute, Cornell Law School. Accessed 2026-11-15.
- FAR 28.102-1 General (FAC 2026-01), Acquisition.gov, GSA (text read via eCFR). Accessed 2026-11-15.
- FAR 28.102-2 Amount required, Acquisition.gov, GSA. Accessed 2026-11-15.
- FAR 28.106-6 Furnishing information, Acquisition.gov, GSA. Accessed 2026-11-15.
- FAR 28.106-7 Withholding contract payments, Acquisition.gov, GSA. Accessed 2026-11-15.
- FAR 52.228-15 Performance and Payment Bonds, Construction (Jun 2020), Acquisition.gov, GSA. Accessed 2026-11-15.
- Payment Bond, Standard Form 25A (Rev. 10/2023), U.S. General Services Administration. Accessed 2026-11-02.
- AIA Document A312-2010 Performance Bond and Payment Bond (Exhibit K, posted December 2024), Housing Opportunities Commission of Montgomery County, MD; form by The American Institute of Architects. Accessed 2026-11-15.
- Treasury Department Circular 570, List of Certified Companies (effective August 1, 2026), U.S. Treasury, Bureau of the Fiscal Service. Accessed 2026-10-18.
- Fla. Stat. 255.05, Bond of contractor constructing public buildings, Florida Legislature. Accessed 2026-11-15.
- Fla. Stat. 713.23, Payment bond, Florida Legislature. Accessed 2026-11-02.
- Code of Virginia 2.2-4337, Performance and payment bonds, Virginia Legislative Information System. Accessed 2026-11-15.
- Code of Virginia 2.2-4341, Actions on payment bonds, Virginia Legislative Information System. Accessed 2026-11-15.
- Texas Government Code chapter 2253 (sections 2253.021, .041, .047, .073, .078), Texas Legislature (text read via a public copy). Accessed 2026-11-15.
- California Civil Code 9550 (with 9554), California Legislative Information (text read via a public copy). Accessed 2026-11-15.
- California Civil Code 9300, California Legislative Information (text read via a public copy). Accessed 2026-11-15.
- California Civil Code 9558, California Legislative Information (text read via a public copy). Accessed 2026-11-15.
- California Civil Code 9560, California Legislative Information (text read via a public copy). Accessed 2026-11-15.
- New York State Finance Law 137, Bond to secure payment of certain claims, New York State Senate (text read via a public copy). Accessed 2026-11-15.
- ORS 279C.380, 279C.600, 279C.605, 279C.610, Oregon State Legislature (text read via a public copy). Accessed 2026-11-15.
- A.R.S. 34-222, Surety bond required, Arizona State Legislature. Accessed 2026-11-15.
- A.R.S. 34-223, Payment bond provisions, Arizona State Legislature. Accessed 2026-11-15.
- Survey of State Bond Thresholds (as of Jan. 1, 2024), National Association of Surety Bond Producers. Accessed 2026-11-15.
- Tabulation of Bids, TG07.2 Structural Concrete Superstructure (February 11, 2014), Transbay Joint Powers Authority. Accessed 2026-11-15.
- Bid Form Comparison Sheet, TG07.3 Miscellaneous Metals (January 22, 2015), Transbay Joint Powers Authority. Accessed 2026-11-15.
- Tabulation of Bids, TG16.8 Fireproofing, Rev. 1 (September 18, 2014), Transbay Joint Powers Authority. Accessed 2026-11-15.
- Sealed Bid Tabulation, Bid 1718-25 Street Painting Services (July 25, 2018), City of Longview, Texas, Office of Purchasing. Accessed 2026-11-15.
- Request for Board Action, Edneyville Elementary GMP (April 2018), Henderson County, North Carolina. Accessed 2026-11-15.
- SBA Surety Bond Guarantee Program, R42037 (updated July 18, 2025), Congressional Research Service (via EveryCRSReport). Accessed 2026-11-15.
- Surety bonds (program page), U.S. Small Business Administration. Accessed 2026-11-02.